Sungi Development Foundation
Housing Reconstruction & Rehabilitation Capacity Building Project
 
MUZAFFARABAD - Progress report upto January 20' 2007
Sr. # HRC Unit UC Community Meetings VRC Formation Social Mobilization Technical Trainings
No. of Meetings Participants Men Women Joint Total Village Profile Village Map Dream Map Procurement Committee ToTs Trainings ToTs Trainings (Self Conducted)
Men Women Total Social Organizers VRC Orientation No. of ToTs Engineer Sub-Engineer Artisans/ Masons Total No. of Trainings Masons Carpenters Steel Fixers Self Builders Total
No. of ToTs No. of Participants Total No. of Trainings Men Women Total
1 Hattian Langla 53 1175 435 1610 3 3 23 29 29 29 29 29 2 19 19 29 240 160 400 1 1 2 0 3 10 85 34 20 51 190
2 Muzaffarabad Chanal Bang 46 935 410 1345 2 2 17 21 21 21 21 21 21 195 105 300 7 60 14 8 30 112
3 Langar Pura 40 1140 510 1650 0 0 21 21 21 21 21 21 21 205 170 375 2 55 11 10 15 91
Sub. Total 139 3250 1355 4605 5 5 61 71 71 71 71 71 2 19 19 71 640 435 1075 1 1 2 0 3 19 200 59 38 96 393
 
ABBOTTABAD - Progress report upto 1st December' 2006
Sr. # HRC Unit UC Community Meetings VRC Formation Social Mobilization Technical Trainings
No. of Meetings Participants Men Women Joint Total Village Profile Village Map Dream Map Procurement Committee ToTs Trainings ToTs Trainings (Self Conducted)
Men Women Total Social Organizers VRC Orientation No. of ToTs Engineer Sub-Engineer Artisans/ Masons Total No. of Trainings Masons Carpenters Steel Fixers Self Builders Total
No. of ToTs No. of Participants Total No. of Trainings Men Women Total
4 HRC Muzaffarabad Chammad 11 180 120 300 6 5 0 11 11 11 11 11 2 6 6 12 110 75 185 2 1 3 0 4 1 12 10 1 7 30
5 Salhad 8 60 85 145 0 5 0 5 5 5 5 5 5 35 20 55            
6 Kakul 9 110 70 180 0 2 0 2 1 1 1 1 1 25 20 45            
7 Kathwal 15 134 122 256 7 8 0 15 14 14 14 14 14 170 110 280 1 17 6 6 0 29
8 Beerangali 28 90 60 150 11 17 0 28 11 11 11 11 11 145 120 265 1 17 2 1 3 23
9 Bakot 11 140 110 250 11 0 0 11 7 7 7 7 7 90 60 150 1 25 5 4 1 35
10 Numal 18 63 41 104 10 8 0 18 12 12 12 12 12 180 95 275 2 19 20 8   47
Sub. Total 100 777 608 1385 45 45 0 90 61 61 61 61 2 6 6 62 755 500 1255 2 1 3 0 4 6 90 43 20 11 164
 
BATTAGRAM - Progress report upto January 20' 2007
Sr. # HRC Unit UC Community Meetings VRC Formation Social Mobilization Technical Trainings
No. of Meetings Participants Men Women Joint Total Village Profile Village Map Dream Map Procurement Committee ToTs Trainings ToTs Trainings (Self Conducted) One Day Sessions for Self Builders
Men Women Total Social Organizers VRC Orientation No. of ToTs Engineer Sub-Engineer Artisans/ Masons Total No. of Trainings Masons Carpenters Steel Fixers Self Builders Total Sessions Self Builders Trained
No. of ToTs No. of Participants Total No. of Trainings Men Women Total
11 Bannah Rashang 167 1912 0 1912 48 0 0 48 48 48 48 48 1 4 4 48 726 0 726 3 0 3 35 38 5 165 14 3 0 182 6 410